Task record
- Task ID
- MT-2045
- Zone
- Z-C1 — Pier C1
- Assignee
- Roof Maintenance Team B
- Created
- 2026-07-21
- Due date
- 2026-08-06
- Progress
- 100%
- Priority
- High
- Status
- Completed
Work instruction
Full membrane patch, verify with water test.
Before / after evidence


Activity history
- 2026-07-21Task created from approved finding — Eng. Sok Dara
- 2026-08-05Assigned with priority and due date — Eng. Chan Vibol
- 2026-08-08Progress updated to 100% — Roof Maintenance Team B
- 2026-08-09Awaiting CAIC verification — CAIC Engineering