Task record
- Task ID
- MT-2041
- Zone
- Z-A1 — Terminal Roof A1
- Assignee
- Roof Maintenance Team A
- Created
- 2026-08-03
- Due date
- 2026-08-14
- Progress
- 60%
- Priority
- High
- Status
- In Progress
Work instruction
Clean joint, apply primer and PU sealant, restore silica top coat.
Before / after evidence


Activity history
- 2026-08-03Task created from approved finding — Eng. Sok Dara
- 2026-08-05Assigned with priority and due date — Eng. Chan Vibol
- 2026-08-08Progress updated to 60% — Roof Maintenance Team A
- 2026-08-09Awaiting CAIC verification — CAIC Engineering