Seal 2.4 mm joint crack - Terminal Roof A1

MT-2041 · Terminal Roof A1 · created 2026-08-03

← Back to tasks

Task record

Task ID
MT-2041
Zone
Z-A1 — Terminal Roof A1
Assignee
Roof Maintenance Team A
Created
2026-08-03
Due date
2026-08-14
Progress
60%
Priority
High
Status
In Progress
Linked finding CR-001

Work instruction

Clean joint, apply primer and PU sealant, restore silica top coat.

Upload evidence

Before / after evidence

Before repair condition
Before — 2026-08-03
After repair condition
After — sealant applied, silica top coat restored

Activity history

  1. 2026-08-03Task created from approved finding Eng. Sok Dara
  2. 2026-08-05Assigned with priority and due date Eng. Chan Vibol
  3. 2026-08-08Progress updated to 60% Roof Maintenance Team A
  4. 2026-08-09Awaiting CAIC verification CAIC Engineering